Prioritization Matrix

Prioritization is a technique used to determine which maintenance and rehabilitation (M&R) activities should be performed when insufficient funding exists to perform all recommended work. The prioritization scheme developed by ADOT is referred to as the Pavement Priority Rating Number (PPRN) system, and it prioritizes pavement sections based on a combination of pavement use and pavement condition. The details of the ADOT PPRN are presented in the table below. Priority numbers range from 1 to 27 in the table, with 1 being the highest priority.

Table 1. Summary of the ADOT PPRN system.
Use PCI Range for NPIAS Airports PCI Range for Non-NPIAS/Unclassified Airports
100-86 85-71 70-56 55-41 40-0 100-86 85-71 70-56 55-41 40-0
Primary Runways 5 3 4 6 23 5 3 4 1 23
Taxiways 9 7 8 10 24 9 7 8 2 24
Aprons 13 11 12 14 25 13 11 12 14 25
Secondary Runways 17 15 16 18 26 17 15 16 18 26
T-hangars/Helipads 20 19 21 22 27 20 19 21 22 27